122 – 130 Cosgrave Rd

Project Type
Land Development
Region/Location
Papakura
Start Date
March 2022
Completion Date
February 2023

Site preparation and earthworks including:

  • Installation of erosion and sediment controls
  • Demolition and clearing of existing structures and land
  • Cut and fill of land to desired earth work levels

Installation of civil infrastructure including:

  • Wastewater and stormwater drainage
  • Common service trenches and service installations
  • Kerb and channel, footpath, driveway, joal (right of way), parking areas
  • Road pavement construction and sealing
  • Planting of flora and fauna and landscaping.